Latest news
COVID-19 and Viking Link construction works
The construction of Viking Link is a key part of the development of national infrastructure for the UK and Denmark. The two partners, National Grid and Energinet, together with our contractors, have assessed the COVID-19 impacts on the manufacturing and construction works. In line with current government guidelines in Denmark, Great Britain and the countries involved in the manufacturing of cables and converters, essential work on the Viking Link interconnector project continues. Some of the activities are works that need to take place today, to ensure the running of the network tomorrow.
The welfare of our employees and contractors remains our priority. All the people who need to continue working on site and in the community are doing so under stringent health and safety measures to protect not just themselves but also the communities in which they operate.
We are very grateful to our people who are continuing to go out to work every day to continue the construction of the energy networks of tomorrow at such a critical time.
Archive
- August 2023
- July 2023
- May 2023
- December 2022
- November 2022
- May 2021
- March 2021
- December 2020
- September 2020
- August 2020
- July 2020
- June 2020
- March 2020
- February 2020
- December 2019
- October 2019
- September 2019
- July 2019
- June 2019
- December 2018
- November 2018
- October 2018
- April 2018
- November 2017
- October 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- March 2017
- December 2016
- October 2016
- September 2016
- August 2016
- July 2016
- June 2016
- May 2016
- April 2016
- December 2015
- November 2015