Latest news
Energinet takes first steps to install the land cable
Our contractor Munck Piping has started horizontal directional drilling (HDD) on the Viking Link land cable route in Denmark from Houstrup Beach near Blaabjerg to the converter station in Revsing by Vejen.
Horizontal directional drilling is used to avoid digging and making an open cable trench in areas where you need to reduce disturbance from construction work - for example when crossing roads, railways and water streams, etc. With this technique it is possible to drill underneath these obstacles.
At the end of 2019, we concluded the first long HDD under the dunes at Houstrup Beach, Denmark. The remaining HDD's will primarily be at cable crossings for roads and railways. The route for the land cable goes through the municipalities of Varde and Vejen. A total of 92 horizontal directional drills are planned on the Danish part of the land cable. Of these, 40 are expected to be completed before the end of 2020. After this, there will be a winter break before we resume the drilling works during the spring 2021.
Archive
- August 2023
- July 2023
- May 2023
- December 2022
- November 2022
- May 2021
- March 2021
- December 2020
- September 2020
- August 2020
- July 2020
- June 2020
- March 2020
- February 2020
- December 2019
- October 2019
- September 2019
- July 2019
- June 2019
- December 2018
- November 2018
- October 2018
- April 2018
- November 2017
- October 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- March 2017
- December 2016
- October 2016
- September 2016
- August 2016
- July 2016
- June 2016
- May 2016
- April 2016
- December 2015
- November 2015